PROJECT OVERVIEW
Children’s Hospital
Our assignment was not only to design, value-engineer, and fabricate the steel, we imported IMP from Spain, provided all doors and windows, along with drywall, studs, sinks, and even toilets. To make it even more challenging, the client needed everything shipped on one-single vessel, almost 200 containers. We had to assemble all the steel, panels, and accessories in a warehouse we rented in order to package and ship all materials at once. All this occurred within 6 months from start to finish, that’s some special coordination!
PROJECT HIGHLIGHTS
Dimensions: 16+ bldg
Total Square Footage: 310,000
Industry: Community